Force Majeure Clause

A force majeure clause is the contract term that suspends, rather than cancels, both parties' obligations under a wafer supply or capacity agreement when a qualifying event outside either party's reasonable control, such as a natural disaster, war, or government export ban, makes performance impossible or illegal.

What a Force Majeure Clause Actually Suspends obligations pause during the event, they are not simply erased Normal operation Take-or-pay floor enforced Delivery deadlines enforced triggered by: earthquake, fire, export ban, or pandemic Force majeure declared Floor obligation suspended Deadlines suspended Event ends, notice given, obligations resume neither side owes damages for the suspended period itself The clause only covers events named or described in the contract's own definition. An ordinary cost increase or a predictable delay almost never qualifies.

Suspension is the key word, and it is narrower than people assume. A force majeure event pauses a take-or-pay floor or a delivery deadline for the duration of the event, but it does not erase the underlying contract, cancel future obligations once the event ends, or automatically excuse a delay that was foreseeable or that the invoking party failed to reasonably mitigate.

Qualifying event occurs
natural disaster, war, export ban, pandemic
Invoking party must prove the clause appliesburden of proof sits with whoever invokes it
Event matches the contract's own definition
not just inconvenient or costly
Give formal notice within the required window
late notice can forfeit the protection
Show reasonable mitigation was attempted
courts expect good-faith effort to reduce harm
Obligations suspended, not canceled
resume once the event ends

The clause only covers what it actually names or describes. Most foundry contracts list specific qualifying categories, natural disasters, war, government action, labor disputes, rather than relying on a vague general standard, which means a party trying to invoke force majeure for an event the contract does not clearly cover, such as an ordinary commodity cost spike, is usually better served by the contract's own price escalation clause instead.

EventTypically coveredTypically not covered
Earthquake or natural disasteryes, almost always named explicitly—
Government export ban or sanctionoften yes, increasingly named post-2020a company's own compliance failure
Pandemic / public health ordercontested, varies by contract vintageordinary seasonal illness or absence
Commodity price spikealmost never on its ownthis is what escalation clauses are for
Labor strikesometimes, if nameda strike the company's own conduct provoked

Taiwan's earthquake exposure makes this clause unusually load-bearing for the whole industry. TSMC has invoked force majeure-style provisions and issued public statements about fab operations after significant earthquakes, and because so much leading-edge capacity sits on one seismically active island, every major customer's supply agreement has to account for the real possibility that a single geological event could trigger this clause across multiple contracts simultaneously.

Post-2020 contracts increasingly name pandemics and export controls explicitly. Older agreements written before COVID-19 and before the broadened US-China export restrictions often left those categories ambiguous under general language like "acts of government" or "epidemic," which produced real disputes over coverage; newer contracts in the industry now tend to spell out pandemic response and export-control scenarios as their own named categories specifically to avoid relitigating that ambiguity.

Read a force majeure clause through a *risk-of-the-uncontrollable* lens rather than an *excuse clause* lens: it exists to answer one narrow question, who bears the cost when neither side did anything wrong and the world simply made performance impossible, and the answer it gives is almost always a pause, not a cancellation, with both parties expected to pick the contract back up the moment the qualifying event actually ends.