Force Majeure Clause
A force majeure clause is the contract term that suspends, rather than cancels, both parties' obligations under a wafer supply or capacity agreement when a qualifying event outside either party's reasonable control, such as a natural disaster, war, or government export ban, makes performance impossible or illegal.
Suspension is the key word, and it is narrower than people assume. A force majeure event pauses a take-or-pay floor or a delivery deadline for the duration of the event, but it does not erase the underlying contract, cancel future obligations once the event ends, or automatically excuse a delay that was foreseeable or that the invoking party failed to reasonably mitigate.
The clause only covers what it actually names or describes. Most foundry contracts list specific qualifying categories, natural disasters, war, government action, labor disputes, rather than relying on a vague general standard, which means a party trying to invoke force majeure for an event the contract does not clearly cover, such as an ordinary commodity cost spike, is usually better served by the contract's own price escalation clause instead.
| Event | Typically covered | Typically not covered |
|---|---|---|
| Earthquake or natural disaster | yes, almost always named explicitly | — |
| Government export ban or sanction | often yes, increasingly named post-2020 | a company's own compliance failure |
| Pandemic / public health order | contested, varies by contract vintage | ordinary seasonal illness or absence |
| Commodity price spike | almost never on its own | this is what escalation clauses are for |
| Labor strike | sometimes, if named | a strike the company's own conduct provoked |
Taiwan's earthquake exposure makes this clause unusually load-bearing for the whole industry. TSMC has invoked force majeure-style provisions and issued public statements about fab operations after significant earthquakes, and because so much leading-edge capacity sits on one seismically active island, every major customer's supply agreement has to account for the real possibility that a single geological event could trigger this clause across multiple contracts simultaneously.
Post-2020 contracts increasingly name pandemics and export controls explicitly. Older agreements written before COVID-19 and before the broadened US-China export restrictions often left those categories ambiguous under general language like "acts of government" or "epidemic," which produced real disputes over coverage; newer contracts in the industry now tend to spell out pandemic response and export-control scenarios as their own named categories specifically to avoid relitigating that ambiguity.
Read a force majeure clause through a *risk-of-the-uncontrollable* lens rather than an *excuse clause* lens: it exists to answer one narrow question, who bears the cost when neither side did anything wrong and the world simply made performance impossible, and the answer it gives is almost always a pause, not a cancellation, with both parties expected to pick the contract back up the moment the qualifying event actually ends.