Last Time Buy
A last-time-buy (LTB) notice is the formal announcement that a specific part, process, or wafer line is being discontinued, giving customers one final, fixed window to place an order covering their entire remaining lifetime demand before that manufacturing capability disappears for good. Where every other contract term in this cluster, take-or-pay, requirements, price-escalation, governs an ongoing supply relationship, a last-time-buy is the mechanism that formally ends one: it converts an open-ended future obligation into a single, final, unrepeatable order, which is why getting the forecast right at that moment matters more than it does for any routine periodic order.
The notice period itself is a negotiated term, not a courtesy, because the customer needs enough lead time to calculate lifetime demand, qualify an alternative part if one exists, or redesign around the discontinuation, while the foundry needs a firm cutoff date to actually free the capacity, tooling, or wafer line the discontinued part was occupying. Industry practice typically targets six to twelve months of notice for mature, broadly-used parts, but the right number depends on how hard the part is to re-source: a widely second-sourced commodity part needs far less notice than a sole-sourced part with no qualified alternative anywhere in the market.
This single-shot structure pushes the entire forecasting risk onto the customer in a way routine ordering never does — underestimating demand on a normal periodic order just means placing another order next cycle, but underestimating lifetime demand at a last-time-buy means the part becomes permanently unobtainable through normal channels, forcing the customer into expensive aftermarket sourcing, a costly redesign, or outright discontinuation of whatever product depended on that part.
| Decision | Risk if too conservative | Risk if too aggressive |
|---|---|---|
| Order quantity | Permanent shortage once the line is gone | Excess inventory tying up capital for years |
| Notice period requested | Insufficient time to forecast or redesign | Foundry delays freeing the capacity it needs |
| Alternative-sourcing plan | Scrambling for a substitute after supply ends | Unnecessary qualification cost if LTB stock suffices |
A last-time-buy is the one point in a foundry relationship where every risk-sharing mechanism covered elsewhere in this cluster, take-or-pay volume, price escalation, yield guarantees, becomes irrelevant all at once — once the final order ships, there is no contract left to renegotiate.