Semi E10
SEMI E10 defines the standard state model and time-category definitions that every piece of fab equipment's uptime is measured against, which is why "E10 states" and "E10 availability" are phrases fab operations teams use constantly even when they've never read the document itself. Before E10, two fabs — or even two tools in the same fab from different vendors — could each report "95% uptime" while quietly using different definitions of what counts as downtime, making the numbers impossible to compare; E10 solves that by defining a fixed set of equipment states (productive, standby, engineering, scheduled downtime, unscheduled downtime, non-scheduled time) and the exact formulas for deriving availability, utilization, and reliability metrics from the time an equipment tool spends in each one.
The categorization that causes the most disagreement in practice is the line between unscheduled downtime and engineering time, because a tool that's down for an unplanned repair counts against availability while the exact same tool running an engineering experiment on the same unplanned afternoon does not — so two fabs applying E10 honestly can still disagree about a borderline case unless their local work rules for state assignment are documented as precisely as E10's own definitions are. This is also why E10 metrics are only safely comparable between tools, vendors, or fabs when everyone involved has agreed on the same state-assignment rules for the ambiguous cases, not just adopted the standard's headline formulas — the formula was never the hard part, consistent state bookkeeping underneath it is.
SEMI E10 is a metrics and vocabulary standard, not a communication protocol — it does not define how equipment reports its state (that's SECS/GEM's job via E30 and the Equipment Performance Tracking standard E116), only what the state categories mean and how availability, utilization, and reliability are calculated once that state data exists, which is why E10 numbers are often the headline metric a fab reports up through its Overall Equipment Effectiveness and Overall Factory Efficiency (SEMI E124) rollups.