site acceptance test
**Site acceptance test** is the **post-installation verification that confirms equipment performs correctly in the customer facility environment after delivery and hookup** - it proves shipping, installation, and utility integration did not compromise tool readiness.
**What Is Site acceptance test?**
- **Definition**: SAT phase executed at the fab after mechanical install, utility connection, and safety clearance.
- **Validation Focus**: Facility interfaces, subsystem operation, alarms, and key readiness checks under site conditions.
- **Environment Difference**: Verifies behavior with customer power, gases, water, exhaust, and network controls.
- **Release Context**: Successful SAT typically enables transition to process qualification stages.
**Why Site acceptance test Matters**
- **Integration Assurance**: Confirms tool and facility interfaces are correct before process-critical work begins.
- **Shipping Damage Detection**: Identifies transport-induced misalignment or latent component failures.
- **Safety and Compliance**: Validates interlocks and utility behavior under actual site constraints.
- **Startup Risk Reduction**: Prevents hidden installation issues from appearing during production qualification.
- **Accountability Clarity**: Documents whether open issues belong to vendor delivery or site integration.
**How It Is Used in Practice**
- **SAT Checklist**: Use standardized tests aligned to FAT baselines and site-specific requirements.
- **Gap Closure**: Log and resolve SAT deviations before advancing to PQ or production release.
- **Handover Evidence**: Maintain signed SAT package as part of qualification and audit records.
Site acceptance test is **a required installation-integrity checkpoint in tool commissioning** - passing SAT confirms the equipment is correctly integrated and ready for process capability verification.